Saturday 27 October 2012

Week Five ends
the kitchen units ready to be fitted

into the new kitchen

just a forest of wires - to be plastered on Monday

more units waiting under more wires

a wall waiting for a new window

Oadby's Door of Faith (opening soon)

steel girders to hold up the canopy


Sunday 21 October 2012

By the end of the fourth week


 the pillar is gone
 
and the new window opening is complete
and the old entrance doors are gone
 
and from the outside
 

nearly ready for the new doors and canopy.
Work has commenced inside on improvements to the lighting and heating,
and getting ready to fit the new kitchen.

Friday 12 October 2012

End of the third week
That's a big piece of steel holding up the roof 

Chipping away at the brick pier
View from the other end of the parish room

 
 

The new exterior wall nearly ready for a window



Friday 5 October 2012

At the end of the second week
Don't worry - it's only a temporary door

the footings of the new wall reach ground level

getting ready for the fancy brickwork

Tuesday 2 October 2012

After the weekend work continues
The old screens are gone now

Just a few bits of metal holding the roof up
until the steel joists are put in

The partion where the new door will be

Old and (nearly) New side by side


Views of the parish room from the other end

'Try to enter by the narrow door'
or is it
'Form an orderly queue here, please.'